The modern Martha Mine

In the 1970s the gold price was relatively high. This sparked renewed interest in gold at Waihi. In contrast to the early mining on Martha Hill, environmental considerations were, and remain, a primary consideration in the planning and operation of mining projects.

1976: Waihi Mining and Development (Mineral Resources and Green & McCahill) obtained a Prospecting Licence on Martha Hill.

1979: Prospecting commenced on Martha Hill under a joint venture comprising Waihi Mining and Development, and Amax Exploration (New Zealand) Inc.

1985: The joint venture participants, now joined by Goodman Mining and United Gold Mines, submitted a Mining Licence Application and Environmental Impact Report.

1986: Water Rights applied for in January and Hearing held in August / September.

1987: Mining Licence Hearing commenced 26th January and concluded 27th March. Mining Licence granted 16th July and Water Rights issued 24th July. Construction activities commenced on 18th July and the present Waihi Gold Mining Company was formed.

Work began to establish Gilmour Lake to replace Mine Lake which formed during the 1960s over a section of the old workings known as the Milking Cow.

1988: 15th May – First gold pour.

15th June – Official opening of the new Martha Mine. By December 26th the first tonne of bullion had been poured.

1989: Mine dewatering began in October.

1991: First grazing of cattle on rehabilitated Waste Rock Embankment.

1993: January – Gilmour Lake handed over to the Hauraki District Council.

1994: January – First Martha Mine Open Day.

1995: January – Martha Mine Open Day.

February. Consultation commenced on the Extended Project proposals, continued throughout the permitting process, and is ongoing.

April – H.E.L.P the Habitat Enhancement and Landcare Partnership implemented.

1996: January – Martha Mine Open Day, $50,000 donated to the planned Waihi Events Centre.

Waihi Gold Mining Company announced Extended Project proposals.

1997: July – Extended Project Description completed. Applications lodged with Waikato Regional Council, Hauraki District Council, and Ministry of Commerce. These were accompanied by an Assessment of Environmental Effects and approximately thirty technical reports describing various aspects of the project in detail.

August – September – The Resource Management Act applications were publicly notified and the public made submissions on the project.

November – A Joint Hearing (involving both the Waikato Regional Council and Hauraki District Council) commenced. The Company presented evidence and members of the public also made submissions to the Hearings Committee.

1998: January – Martha Mine Open Day.

March – The decision from the Joint Hearing was received. This was followed by a period of time in which all parties could appeal the decision and/or the conditions proposed for the Extended Project. The appeal period to the Environment Court for the RMA applications ended 31 March.

August – September. Hearing of the RMA appeals, and the variation of the Mining Licence applications by the Environment Court.

December – Decision of the Environment Court received. Resource Consents granted to extend mine life to 2007.

1999: January – Work on the Extended Project commenced.

February – Subsidence and collapse of an area 40 metres in diameter occurred above the old Royal Workings. It involved the same mechanism, and was in the same area, as the 1961 collapse.

July – Martha Mine Education Centre building completed.

December – Extended Project infrastructure in place.

2000: Upgraded crushing, conveying, processing, and Water Treatment Plant commissioned.

June – Martha Mine Education Centre opened.

October –The one millionth ounce of gold was poured.

2001: Barry Road subsidence occurred above old workings on the Royal Lode.

2002: Newmont Mining Corporation took over ownership of Waihi Gold Mining Company.

2003: May – Waihi Community Consultative Committee (WCCC) formed as a community liaison forum.

August – Golden Legacy Centre opened to provide information to the community about Favona, exploration and ‘Golden Legacy’ rehabilitation concepts.

2004: June – Company name changed to Newmont Waihi Gold Limited.

August – Favona underground mine permitting process was completed.

November – Ceremony held to mark the opening of the Favona portal.

2005: January – Construction began on Stage One of the Favona decline tunnel.

January – 1.5 millionth ounce of gold was poured.

February – Martha Mine Open Day.

2006: January – Cornish Pumphouse relocation project strengthening and earthworks began.

September – Open pit stability cutback began, mining in open pit extended to 2010.

November – Cornish Pumphouse relocation complete. Favona ore extraction commenced.

2007: Exploration drilling focused on west and east of open pit as well as continued exploration drilling in the region

December – Opening of new mine interpretation centre ‘Waihi’s Gold Story’ downstairs at the Waihi Visitor Centre

2008: January – Eighth Martha Mine Open Day

May – Twentieth anniversary of the first gold pour and fifth anniversary of Waihi Community Vision (formerly WCCC)

2010: January – ninth Martha Mine Open Day

April – Martha East Layback project began, mining in open pit extended to 2014

June – Grand Junction Refinery building relocated to a site adjacent to the Pit Rim Walkway

December – Public Hearing on Land Use application to Hauraki District Council for Trio Mine Project

2011: January – Trio Consents granted, subject to appeals

2012: Trio production begins, Golden Link/Correnso application

2013: Golden Link/Correnso hearings